Costs below are estimated as of 11/09. As bids are received and awarded this budget will be updated.
| Schematic Design | $93,575 |
| Design Development | $85,050 |
| Construction Documents | $182,700 |
| Bidding | $22,050 |
| Misc. Costs (Studies, admin, etc.) | $25,000 |
| Construction | |
| Administration | $111,625 |
| Construction | $6,000,000 |
| Contingency (5%) | $300,000 |
| Decommission Fairgrounds Arena | $40,000 |
| Land (donated) | $1,600,000 |
| $8,460,000 |